PJMDEM98.4GWFCST104.2GW+5.8LMP$49.36CONG$11.6●RES15.8%●TX8●MIXSrc: · · Upd Oct 10, 2026MISODEM76.5GWFCST84.9GW+8.4LMP$39.82CONG$18.7●RES17.4%●TX10●MIXSrc: · · Upd Oct 10, 2026ERCOTDEM58.9GWFCST66.1GW+7.2LMP$41.20CONG$9.8●RES7.6%●TX12●MIXSrc: · · Upd Oct 10, 2026SPPDEM31.7GWFCST36.2GW+4.5LMP$33.15CONG$6.4●RES21.6%●TX5●MIXSrc: · · Upd Oct 10, 2026CAISODEM27.2GWFCST33.5GW+6.3LMP$63.20CONG$13.9●RES11.4%●TX7●MIXSrc: · · Upd Oct 10, 2026NYISODEM16.1GWFCST19.0GW+2.9LMP$68.40CONG$10.3●RES14.1%●TX4●MIXSrc: · · Upd Oct 10, 2026ISO-NEDEM12.8GWFCST15.4GW+2.6LMP$57.10CONG$7.9●RES17.2%●TX3●MIXSrc: · · Upd Oct 10, 2026PJMDEM98.4GWFCST104.2GW+5.8LMP$49.36CONG$11.6●RES15.8%●TX8●MIXSrc: · · Upd Oct 10, 2026MISODEM76.5GWFCST84.9GW+8.4LMP$39.82CONG$18.7●RES17.4%●TX10●MIXSrc: · · Upd Oct 10, 2026ERCOTDEM58.9GWFCST66.1GW+7.2LMP$41.20CONG$9.8●RES7.6%●TX12●MIXSrc: · · Upd Oct 10, 2026SPPDEM31.7GWFCST36.2GW+4.5LMP$33.15CONG$6.4●RES21.6%●TX5●MIXSrc: · · Upd Oct 10, 2026CAISODEM27.2GWFCST33.5GW+6.3LMP$63.20CONG$13.9●RES11.4%●TX7●MIXSrc: · · Upd Oct 10, 2026NYISODEM16.1GWFCST19.0GW+2.9LMP$68.40CONG$10.3●RES14.1%●TX4●MIXSrc: · · Upd Oct 10, 2026ISO-NEDEM12.8GWFCST15.4GW+2.6LMP$57.10CONG$7.9●RES17.2%●TX3●MIXSrc: · · Upd Oct 10, 2026
SMStock & Milster

Sample Deliverable

Download PDF

STOCK & MILSTER · SAMPLE · SM-DEMO-01

Site Selection Infrastructure Briefing — Sample

Illustrative example — not a client engagement or live market data

01Decision question

Which of three candidate sites should a manufacturer advance for a new facility requiring roughly 120 MW within four years?

02Executive findings

  1. 1Site A offers the strongest long-term cost position, but its timeline depends on a substation upgrade with no committed in-service date in the utility's published plans.
  2. 2Site B has the clearest near-term energization pathway, but limited headroom beyond the first phase.
  3. 3Site C sits in a territory with a pending rate case whose outcome could materially change forward energy cost.
  4. 4No site is clearly superior on all criteria; the decision turns on how leadership weighs schedule certainty against long-term cost.

03Evidence and source dates

Source typeUsed forDate treatment
Utility integrated resource plan (public filing)Planned generation and load assumptions by territoryFiling date recorded per source
Transmission operator regional planPlanned upgrades near each site and stated in-service windowsPlan vintage recorded per source
State utility commission docketPending rate case and rider proposalsDocket status as of review date
Interconnection / large-load queue recordsCompeting requests near each substationQueue snapshot date recorded

04Infrastructure dependencies

Site A

  • — Substation expansion (uncommitted)
  • — Transmission line reconductoring
  • — Utility large-load study

Site B

  • — Existing feeder capacity (phase 1)
  • — Future transformer addition (phase 2)

Site C

  • — Rate case outcome
  • — Regional transmission project timing

05Assumptions

  • — Load requirement of roughly 120 MW with a two-phase ramp.
  • — Published utility and transmission plans are treated as indicative, not commitments.
  • — No private utility correspondence was available for this sample.

06Uncertainty

  • — Upgrade timing at Site A could move by several years in either direction.
  • — Rate case outcomes at Site C are unknown until a commission order.
  • — Competing large-load requests could absorb Site B's headroom.

07Scenario comparison (qualitative)

ScenarioSite ASite BSite CRead
Schedule priorityWeakStrongModerateFavors Site B if the first phase must energize on time.
Long-term cost priorityStrongModerateUncertainFavors Site A if the schedule can absorb upgrade risk.
Adverse regulatory outcomeModerateModerateWeakSite C's position deteriorates if the rate case is filed-as-proposed.

08Open diligence questions

  • — Will the utility provide a written capacity and timing indication for Site A?
  • — Can Site B's phase-two capacity be reserved, and on what terms?
  • — What is the expected decision date in Site C's rate case?
  • — Are there competing large-load requests not yet visible in public queue data?

09Decision implications

  • — If schedule certainty is paramount, advance Site B and research phase-two options in parallel.
  • — If long-term cost dominates, advance Site A only after obtaining a utility timing indication.
  • — Defer Site C until the rate case outcome is clearer.

Sample deliverable. Sites, findings and scenarios are fictional and demonstrate structure and method. Not investment, legal, or engineering advice.